Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide a further update on the progress of construction activities at its 100% owned Hombre Muerto West (HMW) Phase 1 lithium brine project, with lithium chloride production expected in H1 2025. Galan continues its steady progress in advancing its low cost, high grade HMW project to production in a timely manner. Filling of pond 2 has commenced, evaporation process is underwayPond 2 earthworks and liner installation progressing well (65% complete)Pond 3 earthworks construction work well under way (40% complete)Pond 1 evaporation continuing, containing approximately 500t LCE alreadyTen (10) production wells completed; only six are required for Phase 1The HMW production process uses very little fresh water and considerably less water than subsequent conversion to lithium carbonate or hydroxideWater was never intended to be sourced from the Los Patos River; water for the HMW Project will be sourced directly from…